序号 No. |
内容/周期(月) Content/Period(Month) |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 |
/ |
前期商洽:确定合作意向,签订EPC框架协议,直至EPC总包合同生效 Preliminary consultation: determine the cooperation intention, sign the EPC framework agreement, until the EPC general contract comes into effect |
|||||||||||||||
1 |
合同生效及确定设计方案 Validation of contract and determination of design scheme |
● | ||||||||||||||
2 |
初步设计 Preliminary Design |
● | ● | |||||||||||||
3 |
设计初稿的审查及批准 Review and Approve of the preliminary design |
● | ||||||||||||||
4 |
工艺设计确定 Determin of the Industrial Design |
● | ● | ● | ||||||||||||
5 |
签订设备清单及订购制作 Sign equipment list and order production |
● | ● | ● | ● | ● | ● | ● | ||||||||
6 |
设备交单 Documents for equipment |
● | ● | ● | ● | ● | ● | ● | ● | ● | ||||||
7 |
土建工程 Building Projects |
● | ● | ● | ● | ● | ● | ● | ● | ● | ||||||
8 |
设备安装 Equipment Installation |
● | ● | ● | ● | ● | ● | ● | ● | |||||||
9 |
人员培训 Personnel Training |
● | ||||||||||||||
10 |
空负荷试车 Empty load test |
● | ||||||||||||||
11 |
调试、检查、验收、正式交付 Commissioning, testing, acceptance and formal delivery |
● | ● | ● | ● | ● |